Question: 1 / 400

What does the term "turnkey project" mean in healthcare construction?

A project that is ongoing and subject to change

A project that is not fully finished before delivery

A project delivered to the client fully completed and operational

The term "turnkey project" in healthcare construction refers to a project that is delivered to the client fully completed and operational. This concept means that once the construction is finished, the client can immediately start using the facility without needing to make any further modifications or additions. The contractor manages all aspects of the project from planning and design through construction and delivery, thus streamlining the process and minimizing the workload for the client. This approach is particularly beneficial in healthcare construction, where time and operational readiness are critical for patient care and facility functionality.

Other options do not accurately represent the nature of a turnkey project. For example, a project described as ongoing and subject to change does not align with the fixed, completed nature of a turnkey delivery. Similarly, a project that is not fully finished before delivery contradicts the essential characteristic of a turnkey project being entirely ready for use. Lastly, a project that involves only the design phase does not encompass the comprehensive construction and operational criteria inherent in a turnkey project.

Get further explanation with Examzify DeepDiveBeta

A project that involves only the design phase

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy